Set to open its doors from December 2020 the Double Height Studio will be built on our Loughton Campus on the land to the rear of Hatfield House.
This project will deliver a new 300m2 double height studio. The space will be divisible into two smaller, equally sized double height studios.
Date | Details |
April 2020 |
Work begins on double height studios. |
30 November 2020 | External building works complete. |
07 December 2020 | Complete internal refurbishments. |
December 2020 |
Expected completion date. |