Set to open its doors from Autumn 2020, the Causeway Teaching Centre will be built on our Colchester Campus close to our North Towers accommodation.
The Causeway Teaching Centre will create 15 new teaching rooms with an average capacity of 40 persons, over three floors.
There will also be the ability to accommodate larger seminar groups of 80 people as two of the rooms on each level will have folding walls.
The external look of the building will resemble the original North Teaching centre.
Date | Details |
18 March - 1 April 2019 | Relocation of water pipes and data fibres from the site. |
1 April 2019 | Work begins on the Causeway Teaching Centre. |
1 April - 18 April 2019 | Site set up, this includes putting up hoarding and signage. |
23 April - 10 May 2019 | Phase 1 foundations piling. Noise disruption expected. |
13 May - 10 June 2019 | No works taking place during the exam period. |
10 June - 6 August 2019 | Phase 2 foundations this work includes drainage and excavations. Noise disruption expected. |
13 August - 3 September 2019 |
Delivery and installation of modular buildings. |
September 2019 - 20 March 2020 |
Weather proofing and external building finishes. |
20 March - 1 April 2020 |
Removal of scaffolding. |
3 April - 9 May 2020 |
External works include new paths and courtyard paving, drainage, construction of ramps and landscaping. This will will be fairly noisy. |
27 April - September 2020 |
Internal finishes including fitting floor covering, furnishing and IT/AV fit out. |
Autumn 2020 | Expected completion date. |