Tower refurbishment developments

Eddington Tower

Located on the south side of campus, Eddington Tower is one of the six iconic towers. It is currently undergoing a complete refurbishment. This includes a full replacement of lifts, all services and infrastructure. The new modern accommodation is due for completion by Autumn 2020.

Building schedule

Date Details
2 December 2019 Work begins on Eddington Tower.  There will be various pathway closure and route diversions in place
February 2020
Commencement of scaffold installation
Mid March 2020 Scaffold completion
30 April 2020

Completion of heavy demolition and window removal

30 September 2020 Internal finishes
June 2021
Completion of landscaping
Summer 2021 Expected completion date